Interior construction for shops, restaurants, salons, clinics and offices in Fukuoka, Japan

SCHEDULE

Timeline counted back from opening day

  1. 4 months before openingConsultation, choosing candidate properties, pre-lease check
  2. 3 months beforeSigning the lease, hearing and budget allocation, layout proposal
  3. 2.5 months beforeSite survey, construction drawings and estimate, prior consultation with the health center and fire department
  4. 2 months beforeContract, shared schedule, construction application to the building
  5. 1.5 months beforeConstruction starts (demolition, groundwork, equipment, finishes)
  6. 1–2 weeks beforeConstruction complete, health center and fire checks, touch-ups
  7. 1 week beforeHandover, delivery of fixtures and equipment, staff training
  8. Opening dayOpen!

STEPS

Ten steps

  1. STEP1

    Consultation (LINE, email or phone)

    same day

    Tell us your business type, the property (or the area you are looking in), your target opening date and budget.

  2. STEP2

    Pre-lease property check

    1–3 days

    From the listing drawings and photos, we check power, water, gas, exhaust, fire safety and the building's construction rules, and give you a cost range.

    Free consultation on LINE

  3. STEP3

    Hearing and budget allocation

    1–2 weeks

    We hear about your concept and operations, and split the budget between interior, equipment, signs, furniture and a contingency.

  4. STEP4

    Layout proposal and rough estimate

    1–2 weeks

    A first layout of seats and circulation, with a rough estimate by work item.

  5. STEP5

    Site survey and detailed meetings

    1 day or more

    We measure the site and confirm equipment, materials and the building's rules.

  6. STEP6

    Construction drawings and estimate

    2–4 weeks

    Construction drawings and an itemized estimate with quantities and unit prices. Conditions for possible extras are written in advance.

  7. STEP7

    Contract and shared schedule

    about 1 week

    After signing, we share a schedule counted back from your opening day, including inspections and deliveries, and apply to the building for the work.

  8. STEP8

    Construction

    2–6 weeks (depending on size)

    Demolition, groundwork, equipment and finishes. We report progress with photos and record hidden parts before they are covered.

  9. STEP9

    Inspections and handover

    3–7 days

    Health center and fire inspections, touch-ups, and handover with the photo records.

  10. STEP10

    Opening and after-care

    after opening, too

    We stay in touch after opening for adjustments, additions and repairs.

PERMITS

Permits and notifications to check

  • Food business license — restaurants, cafés, takeout

    Apply to the public health center. Consult with your drawings before construction; the premises are inspected before the license is issued.

  • Beauty salon registration — hair salons, eyelash salons

    Notify the public health center and have the facilities checked. Workroom size, lighting, ventilation and materials have standards.

  • Clinic opening notification — clinics

    Notify the public health center (within 10 days of opening for a clinic opened by an individual doctor). X-ray equipment needs its own notification.

  • Notification before use — all businesses

    Notify the fire station before you start using the premises. In Fukuoka City, the fire bureau asks for this at least 7 days before use and for consultation at the planning stage.

  • Building rules — tenant spaces

    Most buildings set work hours, delivery routes and B work done by designated contractors. Drawings may need the building's approval.

General information as of September 2026. Rules and procedures can change, so check with the relevant office (public health center, fire station, Fukuoka City). Applications are made by the owner; the drawings used for prior consultations are prepared as part of our design work.

GLOSSARY

Japanese terms you will hear

Tsubo (坪)
A Japanese unit of floor area: 1 tsubo ≈ 3.3 m² (about 35.6 sq ft). Rents and interior costs are often quoted per tsubo.
Skeleton (スケルトン)
A unit handed over as bare concrete, with no finishes or equipment.
Inuki (居抜き)
A unit leased with the previous tenant's interior and equipment left in place. It can save cost and time, but check what actually works before you sign.
Zosaku joto (造作譲渡)
Handing over the previous tenant's fixtures and equipment, sometimes for a fee. Leased items belong to the leasing company, not the previous tenant.
Genjo kaifuku (原状回復)
Returning the premises to the condition agreed in the lease when you move out. Commercial leases often require more than residential ones.
A, B and C work (A・B・C工事)
How work is divided in Japanese commercial buildings. A: done and paid for by the owner. B: requested and paid for by the tenant but done by the owner's designated contractor (e.g. air conditioning, fire systems). C: done by the tenant's own contractor at the tenant's cost.
Hokenjo (保健所)
The public health center. It issues food business licenses and checks beauty salons and clinics. Consult it with your drawings before construction.

CONTACT

Free rough estimate for your shop interior

You can consult us before you sign a lease. Send floor plans or photos on LINE, and we will tell you the likely cost range and how to proceed.